 |
|
Architect: Philip Johnson and Architects Design Group
Size: 500,000 square feet
Cost: $23,000,000
Completion: 1972
LeMessurier Consultants provided structural engineering
services from schematic design to final working drawings and construction
inspection for this project. The site, in the Copley Square area of
Back Bay, Boston, has streets on three sides and adjoins the historic
1895 Central Library, designed by McKim, Mead & White and considered
a landmark of American architecture.
Some features of the $23 million dollar structure include:
-7 above grade and 2 below grade floors, a total of 500,000 sq. ft.
-Flat concrete slab upper floors three through six are hung from a main
grid of story-depth interconnecting trusses, most of which also span
the building's nine basic 58-foot bays. Three of the hanging floors
will carry book stacks, while a fourth is for library administrative
offices. The 16 foot deep trusses are supported on steel box columns
rising from the basement foundation slab 27 feet below street level,
while some will be supported on 9-foot-deep welded plate girders spanning
58 feet. The lower level of the trusses (bottom chord) carries the seventh
floor for large mechanical equipment (up to 150 pounds per square foot
of live load) and for additional book storage. In floors three through
six, there are similarly high live loads ranging up to 120 psf in book
stack areas. The upper level of trusses (top chord) is designed to support
the sloping steel-framed roof - maintaining almost the same shape as
the existing library roof.
- Welded built-up 32-inch-deep by 10-inch-wide composite plate girders
span 58 feet at the second floor to carry post-tensioned two-way waffle
slabs 60 feet square.
- The engineering incorporates for the first time in buildings, so far
as is known, "orthotropic" pedestrian bridges. These low-profile bridges,
only 19-¼ inches deep and either 6-½ feet or 13 feet wide as required,
span 58-foot open modules at the interior mezzanine level. The term
orthotropic generally refers to the design of a steel plate bridge deck
which serves the double purpose of being a structural member of the
bridge as well as the roadway surface. The library addition bridges
incorporate a 2-¾ inch concrete walking surface held by welded stud
shear connectors to ¼-inch steel plate on 16-inch beams. Among other
advantages, orthotropic design permits construction of very shallow-depth
bridges spanning long distances, as was required in the library addition
to provide necessary headroom between the street and second floors.
- An unusual construction technique was used starting the building from
the bottom, then erecting the main columns and 7th floor trusses and
proceeding from the top down. Temporary bracing was used to tie the
columns together and resist lateral forces until the 2nd through 6th
floors were completed. Because the basement of the new building is right
next to the present library - yet is 18 feet deeper - the subsurface
soil strains was monitored by the use of special instruments. Settlement
movement of both the old and new library buildings and the city streets
during construction was also constantly monitored.
Heavy 7-foot-thick reinforced concrete spread footings up to 40 feet
square are used for foundations. Interconnecting them is a 3-foot pressure
slab designed to resist water uplift of 1,000 pounds per square foot.
The sequence and size of foundation excavations to the clay bearing
stratum was carefully specified and controlled during construction.
Another important problem that had to be solved was
the presence of extensive ground water. Many buildings near the construction
site, including such historic structures as Trinity Church, Old South
Church and the present central library, rest on wooden piles. These
foundations must be kept submerged to prevent rot. To maintain the existing
ground water level, steel sheet piling was driven around the entire
construction site and an elaborate recharging system was set up. The
sheet piling wall resisted intrusion of the surrounding subsurface water
into the pumped-out excavation. Since the sheet piling was not completely
watertight, ground water lost through it was replaced by pumping clean
water into the soil by means of a conventional well point system installed
outside of the sheet piling. Numerous observation wells around the Copley
Square area were checked twice weekly to see that water levels remain
high.
|